Delivering the Tranches

Click to expand guidance.

Managing the Tranches is the combination of processes and activities which keeps the balance between the rates of potential change being delivered by projects with the ability of the organisational to absorb that change.

The activities are designed to ensure that controls are in place and working. They also focus on ensuring that the programme remains aligned to the organisations strategic direction.

Problems with projects and realising the benefits are managed at this level.

Click to expand guidance.

Objective:

Ensure that the direction is aligned with the strategic direction of the business, the aspirations are achievable and the route optimised.

Test that the programme governance framework is working effectively, identify and make necessary improvements to ensure that it is fit for purpose going forward.

Deliver a coherent plan to mobilise and deliver the next Tranche of the programme.

Detail:

As the programme is coming up to the completion of the first and subsequent Tranches it will need to have a strategic review to ensure that it is still aligned with the needs of the organisation.

This activity is part of the assurance plan and, if possible, should be conducted independently to enable an objective view to be taken.

The Governance framework may well have evolved already as part of the programme delivery. This may have affected the way the Strategies have been delivered. This may have left gaps that need to be accounted for.

If the arrangements have remained stable then this is an opportunity to reflect on the lessons of the Tranche and improve the Governance arrangements for the next Tranche, particularly if the nature of the programme is changing, for example, from construction to technology.

This is the activity to develop a more detailed plan for the next Tranche. The overarching Programme Plan will be in place and should have been refined as the programme matured. However, a full review of the plan and in particular, the launch arrangement for the next Tranche, when there could be a significant change to personnel and skills, needs to be thorough.

Themes
Roles

Governance Structure

Click to expand guidance.

Task:

Review the programme governance structure effectiveness.

Review the internal governance arrangements and action lessons learned.

Confirm strategic alignment of the programme outcomes.

Identify additional change activities required to stabilise the services.

Click to expand guidance.

Task:

Review the programme governance structure effectiveness.

Review the internal governance arrangements and action lessons learned.

Confirm strategic alignment of the programme outcomes.

Identify additional change activities required to stabilise the services.

Guidance:

If Programme Assurance has been appointed, they should be involved with the review.

The review should assess the capabilities and skills of the existing Programme Team and propose the necessary changes to the programme structure to ensure the delivery of the next Tranche is optimised, in particular between the use of internal and external resources. Individuals should have performance targets and objectives set.

The nature of the team will change as it moves to the next Tranche. There should be knowledge transfer arrangements in place and it will be necessary to activate the arrangement for recruiting/procuring the team.

There may be additional change activities or opportunities that arise that can be exploited, these may be seen as opportunity risks, but the environment should be scanned to cover this.

The Governance framework may well have evolved already as part of the programme delivery. This may have affected the way the Strategies have been delivered. This may have left gaps that need to be accounted for.

If the arrangements have remained stable then this is an opportunity to reflect on the lessons of the Tranche and improve the Governance arrangements for the next Tranche, particularly if the nature of the programme is changing, for example, from construction to technology.

Input:

Programme governance arrangements

Project gate reviews

Gate reviews from other programmes

Transition Plan

Blueprint for the Programme

Programme plans

Links:

Governance Techniques Page

Output:

Approval of the achievement of the major outcome

Changes to governance arrangements during the transition to the outcome

Management Control

Click to expand guidance.

Task:

Initiate quality reviews of project outputs and performance.

Review and identify lessons from effect of the programme controls.

Ensure that there are acceptance sign offs for the project deliverables.

Ensure that there is business sign off of the outcomes being achieved.

Manage project escalations.

Manage the dependency network to track the programme critical path.

Manage project escalations.

Track effectiveness of project controls and compliance to framework standards.

Track and control inter programme dependencies.

Undertake an assurance review of the testing plan to confirm all elements are in place.

Review the Monitoring and Controls Strategy for effectiveness.

Review the Information Management Strategy for effectiveness.

Review the Quality and Assurance Strategy for effectiveness.

Impact assessment of lessons learned from controls and strategies and raise change requests.

Maintain configuration and change controls.

Monitor impact on physical assets performance.

Click to expand guidance.

Task:

Initiate quality reviews of project outputs and performance.

Review and identify lessons from effect of the programme controls.

Ensure that there are acceptance sign offs for the project deliverables.

Ensure that there is business sign off of the outcomes being achieved.

Manage project escalations.

Manage the dependency network to track the programme critical path.

Manage project escalations.

Track effectiveness of project controls and compliance to framework standards.

Track and control inter programme dependencies.

Undertake an assurance review of the testing plan to confirm all elements are in place.

Review the Monitoring and Controls Strategy for effectiveness.

Review the Information Management Strategy for effectiveness.

Review the Quality and Assurance Strategy for effectiveness.

Impact assessment of lessons learned from controls and strategies and raise change requests.

Maintain configuration and change controls.

Monitor impact on physical assets performance.

Guidance:

At this point the transitions to achieve the outcomes should have been achieved, so the controls will focus on monitoring and tracking transition and project closures.

The achievement of the milestone should include the review of control effectiveness in preparation for the Gate review.

This review should look to establish whether the direction and route are correct.

 It should also look at whether the projects will build the capability that was defined for the Tranche and whether there is a justification for continuing the programme.

The Quality and Assurance Management Strategy should be reviewed and the effectiveness of audit and assurance be evaluated:

Have they happened enough to have had an impact?

Are the recommendations being adopted?

Is there adequate process to support this?

Information Management Strategy should have adequately secured and managed all programme information, including project and business information.

Check that the currency and integrity of information been maintained and associated information attributes been appropriate to the programme. Based on the review the strategy may require amendment.

The Monitoring and Control strategy will cover the interfaces with the projects and business operations, again, this one will require review and improvement.

Review and identify lessons from effect of the programme controls, these could come from the business, from project or any other sources.

Check that the proposed controls for the next Tranche are robust and are appropriate.

Input:

Programme governance strategies

Business performance reports

Project definition information

Project controls document

Project quality reports

Programme Issue Register

Programme plans

Project progress reports

Dependency network

Links:

Management Control Techniques Page

Output:

Project assurance reviews

Programme issue register

Dependency network

Programme plans

Change requests for projects

Change requests to management strategies

Benefits Management

Click to expand guidance.

Task:

Ensure the review identifies potential to increase benefit opportunities.

Review the effectiveness of business performance metrics and benefits forecast confidence and refine.

Confirm the projected benefits and their ownership.

Click to expand guidance.

Task:

Ensure the review identifies potential to increase benefit opportunities.

Review the effectiveness of business performance metrics and benefits forecast confidence and refine.

Confirm the projected benefits and their ownership.

Guidance:

This is a point where benefits will be released and the change has happened, it is also very likely that there will be a lot of other activity to bring other benefits to life

The review should test and challenge the benefit profiles and the realism of the plan, benefits should have been realised or it may be that there is evidence of over optimism which could nullify the programme's value. Updates to Benefit Profiles should be issued based on the experiences to date.

The effectiveness of the Benefits Management Strategy should be assessed, including the suitability of the areas being monitored. Assess whether business performance is being effectively managed through the various controls. If benefits are not appearing, this should be a cause for concern. A Benefit Review should have been undertaken at least once.

Business Performance monitoring should already be in place to track benefits, but they may need to be extended to monitor other factors for negative or positive impact.

Input:

Benefits Realisation Plan

Benefit Profiles

Transition Plan

Links:

Benefits Management Techniques Page

Output:

Review of benefits effectiveness

Updated Transition Plan

Benefits Realisation Plan

Stakeholder Management

Click to expand guidance.

Task:

Gain stakeholder input on direction and alternative approaches.

Review the effectiveness of stakeholder tracking and communications plan impact.

Confirm adequate high impact stakeholder support continues.

Ensure project and programme communications plans are synchronised.

Review the effectiveness of stakeholder tracking and impact of the communications plan.

Maintain regular bulletins.

Deliver launch or major announcement events.

Track stakeholder profiles and perceptions.

Monitor and action stakeholder feedback.

Activate communications to acknowledge the achievements to date.

Click to expand guidance.

Task:

Gain stakeholder input on direction and alternative approaches.

Review the effectiveness of stakeholder tracking and communications plan impact.

Confirm adequate high impact stakeholder support continues.

Ensure project and programme communications plans are synchronised.

Review the effectiveness of stakeholder tracking and impact of the communications plan.

Maintain regular bulletins.

Deliver launch or major announcement events.

Track stakeholder profiles and perceptions.

Monitor and action stakeholder feedback.

Activate communications to acknowledge the achievements to date.

Guidance:

This could be a point of significant achievement, so there may be a lot of communications around business change activities that will need to be managed through the communications plans.

The Stakeholder Profiles should be maintained and reviewed. The individual stakeholder group profiles will be changing and information about them should be updated on a regular basis, a monthly review would be appropriate.

The information to maintain these profiles needs to be tested for accuracy.

The Communications Plan should be active, with clear and consistent messages being delivered effectively.

The review should test levels of support or resistance to the programme and whether they are increasing, if resistance is rising, then alternative directions may be considered.

Business representation in how and when the programmes are delivered will better enable engagement and increase changes of success. The effectiveness of the Stakeholder Management Strategy and Communications Plan should be reviewed, with any changes being made based on lessons learned.

The Communications Plan should include launch activities and how feedback will be managed to ensure optimal communications channels are developed.

Input:

Programme Stakeholder Management Strategy

Stakeholder profiles

Communications plan

Links:

Stakeholder Management Techniques Page

Output:

Updated Programme communications plan

Updated stakeholder profiles

Planning

Click to expand guidance.

Task:

Realign plans to achieve any new requirements.

Review accuracy of planning and project tolerance and adjust accordingly.

Formalise plan for the programme tranches and review.

Project transitions completed.

Click to expand guidance.

Task:

Realign plans to achieve any new requirements.

Review accuracy of planning and project tolerance and adjust accordingly.

Formalise plan for the programme tranches and review.

Project transitions completed.

Guidance:

The reviews should focus on the direction of the programme and the strategy for getting there. Lessons learned on planning, customer performance and rate of change capability should be reflected in a revised plan and the plan for the next Tranche.

Assess the effectiveness of the project controls and internal programme management controls as defined in the Monitoring and Control Strategy to ensure that adequate governance of the projects is being achieved. It may be necessary to tighten or vary the levels of controls based on early experiences. The Dependency Network and planning tools should be reviewed and assessed for effectiveness and ensure the next Tranche has the appropriate toolkit in place. The Resource Management Strategy, the effectiveness of supply chain installation and also development of internal talent may require the plan or strategy to be changed.

The plan should set the pace for the programme and ensure that there are adequate controls in place to enable delivery. There should be focus on the Intermediate Blueprint, but later Tranches may need feasibility work to be undertaken. Any residual projects remaining under the control of the programme should now be terminated.

The main projects should be at Project Stage Gate 7 as their individual outputs will have been implemented and accepted into operations by the business.

Evidence of sign off will be required by the programme and where the projects have not met their quality expectations then plans to remediate should be included in actions that follow this programme milestone.

There may be projects that have not been at Project Stage Gate 7 for a variety of reasons, one may be that they have further stages.

Output:

Risk & Issue Management

Click to expand guidance.

Task:

Undertake risk impact assessment of the changes.

Review risk management effectiveness and implement improvements.

Undertake risk identification review of any new programme threats or opportunities as a result of outcomes.

Update the risk management strategy from lessons learned if necessary.

Remove risks have now passed their proximity from the risk register.

Click to expand guidance.

Task:

Undertake risk impact assessment of the changes.

Review risk management effectiveness and implement improvements.

Undertake risk identification review of any new programme threats or opportunities as a result of outcomes.

Update the risk management strategy from lessons learned if necessary.

Remove risks have now passed their proximity from the risk register.

Guidance:

At this point the level of change relating to this Tranche should be nearing completion so business stability risks should be reducing or should have passed, so this is a good moment.

The review of risk should look at the current aggregated exposure and the nature of the risks. In particular, the focus should be on the risks that affect the organisation's strategy, the ability to achieve the blueprint and realisation of the benefits.

The effectiveness of the Risk Management Strategy should be evaluated. Effectiveness of the escalation routes and the identification of both risks and issues, along with effectiveness of associated processes, including change control, mitigation plans and general levels of engagement will all enable improvements to be made to the approaches.

Output:

Risk management effectiveness review

Risk registers

Resource Management

Click to expand guidance.

Task:

Review effectiveness of resource management, productivity and optimise.

Review the programme resource management plan for the remainder of the tranche.

Review the resource management strategy that will be required for the remainder of the programme.

Click to expand guidance.

Task:

Review effectiveness of resource management, productivity and optimise.

Review the programme resource management plan for the remainder of the tranche.

Review the resource management strategy that will be required for the remainder of the programme.

Guidance:

The achievement of a major outcome means that a significant transition has now happened, so it is the opportunity to review the effectiveness of transition resources as well as delivery resources. Resources to support sustaining the business to achieve benefits may still be needed, the resource plan should be checked for this.

This is a good moment to analyse the effectiveness of business transition resources, the change team and pick up lessons for future transitions and tranches.

Based on the review here, there may be a need to revise the resource management strategy and/or resource management plan for the programme, as well as the impacts on the projects delivering the capability.

Input:

Transition plan performance

Business performance metrics

Resource expenditure plan

Resource Management Strategy

Links:

Resource Management Techniques Page

Output:

Finance and Business Case

Click to expand guidance.

Task:

Refine finance plans to accommodate any changes.

Review effectiveness of financial forecasting and address causes of weakness.

Review the funding strategy and anticipated costs.

Click to expand guidance.

Task:

Refine finance plans to accommodate any changes.

Review effectiveness of financial forecasting and address causes of weakness.

Review the funding strategy and anticipated costs.

Guidance:

The review should principally focus on the ongoing financial viability of the programme and, in particular, the availability of funds to support it. The balance of benefits and costs should have been under review all the way along, this is the opportunity to stand back and re-think against the bigger picture of organisational context.

The review should assess the accuracy of the estimates being provided for costs and benefits. These should be re-forecast and a revised Business Case produced to justify the programme continuing.

Funds to mobilise the programme and put the infrastructure in place need to be ring fenced to ensure availability.

Output:

Commercial

Click to expand guidance.

Task:

Review effectiveness of supply chain productivity and optimise.

Review the procurement strategy effectiveness.

Ensure outstanding commercial changes from the transition have an action owner.

Click to expand guidance.

Task:

Review effectiveness of supply chain productivity and optimise.

Review the procurement strategy effectiveness.

Ensure outstanding commercial changes from the transition have an action owner.

Guidance:

Where there is a major change of supplier, ensure that transition plans are handed over from the incumbent to the replacement.  There are many risks that can be triggered as knowledge may be lost.

At this point, there may be lessons learned about how the procurement was managed that will be valuable to other programmes and future Tranches, the Portfolio Office should be informed.

Outstanding actions may be best handled as programme level issues.

Input:

Output:

Update issue register with outstanding actions

Update the lessons log

Vision & Blueprint

Click to expand guidance.

Task:

Undertake independent review of project output alignment to confirm Blueprint achievement.

Click to expand guidance.

Task:

Undertake independent review of project output alignment to confirm Blueprint achievement.

Guidance:

The Vision Statement for the programme should still be valid; if it is not then the impact on the programme direction should be considered. It is not desirable to change a Vision Statement, but it may be worth considering re-validation and commitment.

There should be a test to ensure that the end Blueprint is still desirable and that there have been no market changes offering more optimised solutions. Ensure assumptions about developments that underpin the Blueprint are still valid and that the strategic direction of the organisation will be supported by this programme. There should be particular focus on the achievability and desirability of the next intermediate Blueprint.

The projects should now have delivered the outcomes in the Blueprint.

There should be lessons about the technical and organisational feasibility of the programme which may require changes to be made to the project or other controls.

Input:

Blueprint for the Programme

Business Performance Data

Project Gate Reviews

Output:

Senior Responsible Owner

Click to expand guidance.

Task:

Organise an assurance review of the strategic direction to ensure it is still valid.

Lead the review of programme performance to date.

Ensure that the key stakeholders will be involved in supporting the launch of next Tranche.

Click to expand guidance.

Task:

Organise an assurance review of the strategic direction to ensure it is still valid.

Lead the review of programme performance to date.

Ensure that the key stakeholders will be involved in supporting the launch of next Tranche.

Guidance:

It is important for your confidence that there is a thorough review and you are being tasked with an achievable programme. If you have doubts, these should be fed into the review, as should reasons why you believe it is unachievable. If the programme is losing its strategic context or momentum or the organisational direction is changing, it is essential that this is considered during these steps.

You have been leading the programme and your impressions, positive or negative should be fed into the review to ensure that areas of weakness are improved and your confidence is increased.

Be aware that there is a change in competence required as you continue to set the pace of delivery and keeping conflicting priorities balanced.

Input:

Output:

Theme tasks for Senior Responsible Owner:

Governance Structure

Task:

Review the programme governance structure effectiveness.

Review the internal governance arrangements and action lessons learned.

Confirm strategic alignment of the programme outcomes.

Identify additional change activities required to stabilise the services.

Guidance:

If Programme Assurance has been appointed, they should be involved with the review.

The review should assess the capabilities and skills of the existing Programme Team and propose the necessary changes to the programme structure to ensure the delivery of the next Tranche is optimised, in particular between the use of internal and external resources. Individuals should have performance targets and objectives set.

The nature of the team will change as it moves to the next Tranche. There should be knowledge transfer arrangements in place and it will be necessary to activate the arrangement for recruiting/procuring the team.

There may be additional change activities or opportunities that arise that can be exploited, these may be seen as opportunity risks, but the environment should be scanned to cover this.

The Governance framework may well have evolved already as part of the programme delivery. This may have affected the way the Strategies have been delivered. This may have left gaps that need to be accounted for.

If the arrangements have remained stable then this is an opportunity to reflect on the lessons of the Tranche and improve the Governance arrangements for the next Tranche, particularly if the nature of the programme is changing, for example, from construction to technology.

Inputs:

Links:

Governance Techniques Page

Outputs

Business Change Manager

Click to expand guidance.

Task:

Test for opportunities to enhance benefits from alternative outcomes and operating models.

Provide input on the effectiveness of governance for the Business Change Team.

Arrange for local business leaders to be involved in the programme launch.

Click to expand guidance.

Task:

Test for opportunities to enhance benefits from alternative outcomes and operating models.

Provide input on the effectiveness of governance for the Business Change Team.

Arrange for local business leaders to be involved in the programme launch.

Guidance:

This will be your opportunity to flag up concerns you may have about the realism of the approach and in particular, any concerns you may have regarding the benefits and level of business change being planned. If the Blueprint is proving unachievable or the Benefits can't be delivered, now is the time to speak up.

From the business perspective, you should consider whether you have had enough influence of the direction and day to day decision making in the programme, if not, now is the time to look for changes.

You may need to reinforce the Change Team to enable it to support you in being effective - the plan must cover this.

Input:

Output:

Theme tasks for Business Change Manager:

Benefits Management

Task:

Ensure the review identifies potential to increase benefit opportunities.

Review the effectiveness of business performance metrics and benefits forecast confidence and refine.

Confirm the projected benefits and their ownership.

Guidance:

This is a point where benefits will be released and the change has happened, it is also very likely that there will be a lot of other activity to bring other benefits to life

The review should test and challenge the benefit profiles and the realism of the plan, benefits should have been realised or it may be that there is evidence of over optimism which could nullify the programme's value. Updates to Benefit Profiles should be issued based on the experiences to date.

The effectiveness of the Benefits Management Strategy should be assessed, including the suitability of the areas being monitored. Assess whether business performance is being effectively managed through the various controls. If benefits are not appearing, this should be a cause for concern. A Benefit Review should have been undertaken at least once.

Business Performance monitoring should already be in place to track benefits, but they may need to be extended to monitor other factors for negative or positive impact.

Inputs:

Links:

Benefits Management Techniques Page

Outputs

Stakeholder Management

Task:

Gain stakeholder input on direction and alternative approaches.

Review the effectiveness of stakeholder tracking and communications plan impact.

Confirm adequate high impact stakeholder support continues.

Ensure project and programme communications plans are synchronised.

Review the effectiveness of stakeholder tracking and impact of the communications plan.

Maintain regular bulletins.

Deliver launch or major announcement events.

Track stakeholder profiles and perceptions.

Monitor and action stakeholder feedback.

Activate communications to acknowledge the achievements to date.

Guidance:

This could be a point of significant achievement, so there may be a lot of communications around business change activities that will need to be managed through the communications plans.

The Stakeholder Profiles should be maintained and reviewed. The individual stakeholder group profiles will be changing and information about them should be updated on a regular basis, a monthly review would be appropriate.

The information to maintain these profiles needs to be tested for accuracy.

The Communications Plan should be active, with clear and consistent messages being delivered effectively.

The review should test levels of support or resistance to the programme and whether they are increasing, if resistance is rising, then alternative directions may be considered.

Business representation in how and when the programmes are delivered will better enable engagement and increase changes of success. The effectiveness of the Stakeholder Management Strategy and Communications Plan should be reviewed, with any changes being made based on lessons learned.

The Communications Plan should include launch activities and how feedback will be managed to ensure optimal communications channels are developed.

Inputs:

Links:

Stakeholder Management Techniques Page

Outputs

Programme Manager

Click to expand guidance.

Task:

Ensure that options for changes of direction are analysed against the operating models and project dossier.

Provide recommended improvements in process effectiveness and decision making.

Formalise the mobilisation arrangements to ensure momentum.

Click to expand guidance.

Task:

Ensure that options for changes of direction are analysed against the operating models and project dossier.

Provide recommended improvements in process effectiveness and decision making.

Formalise the mobilisation arrangements to ensure momentum.

Guidance:

You will have a key role in managing this review. This is mainly about the direction of the programme which is the domain of the SRO and the BCM. You should look to the SRO and BCM to re-affirm their commitment to the blueprint, Business Case and benefits as part of this review of direction.

This is a very important review for you. As you are responsible for the governance arrangements, this is a good opportunity to stand back and decide if you are using the right approach. What lessons can be learned and how can the governance be improved for the future?

The re-mobilisation will largely focus on activating Governance and launching early projects, some may already be in flight. It is worth seeing the launch and re-establishing of the programme as a project in itself, allocating a Project Manager to ensure it is well run.

Input:

Output:

Theme tasks for Programme Manager:

Management Control

Task:

Initiate quality reviews of project outputs and performance.

Review and identify lessons from effect of the programme controls.

Ensure that there are acceptance sign offs for the project deliverables.

Ensure that there is business sign off of the outcomes being achieved.

Manage project escalations.

Manage the dependency network to track the programme critical path.

Manage project escalations.

Track effectiveness of project controls and compliance to framework standards.

Track and control inter programme dependencies.

Undertake an assurance review of the testing plan to confirm all elements are in place.

Review the Monitoring and Controls Strategy for effectiveness.

Review the Information Management Strategy for effectiveness.

Review the Quality and Assurance Strategy for effectiveness.

Impact assessment of lessons learned from controls and strategies and raise change requests.

Maintain configuration and change controls.

Monitor impact on physical assets performance.

Guidance:

At this point the transitions to achieve the outcomes should have been achieved, so the controls will focus on monitoring and tracking transition and project closures.

The achievement of the milestone should include the review of control effectiveness in preparation for the Gate review.

This review should look to establish whether the direction and route are correct.

 It should also look at whether the projects will build the capability that was defined for the Tranche and whether there is a justification for continuing the programme.

The Quality and Assurance Management Strategy should be reviewed and the effectiveness of audit and assurance be evaluated:

Have they happened enough to have had an impact?

Are the recommendations being adopted?

Is there adequate process to support this?

Information Management Strategy should have adequately secured and managed all programme information, including project and business information.

Check that the currency and integrity of information been maintained and associated information attributes been appropriate to the programme. Based on the review the strategy may require amendment.

The Monitoring and Control strategy will cover the interfaces with the projects and business operations, again, this one will require review and improvement.

Review and identify lessons from effect of the programme controls, these could come from the business, from project or any other sources.

Check that the proposed controls for the next Tranche are robust and are appropriate.

Inputs:

Links:

Management Control Techniques Page

Outputs

Risk & Issue Management

Task:

Undertake risk impact assessment of the changes.

Review risk management effectiveness and implement improvements.

Undertake risk identification review of any new programme threats or opportunities as a result of outcomes.

Update the risk management strategy from lessons learned if necessary.

Remove risks have now passed their proximity from the risk register.

Guidance:

At this point the level of change relating to this Tranche should be nearing completion so business stability risks should be reducing or should have passed, so this is a good moment.

The review of risk should look at the current aggregated exposure and the nature of the risks. In particular, the focus should be on the risks that affect the organisation's strategy, the ability to achieve the blueprint and realisation of the benefits.

The effectiveness of the Risk Management Strategy should be evaluated. Effectiveness of the escalation routes and the identification of both risks and issues, along with effectiveness of associated processes, including change control, mitigation plans and general levels of engagement will all enable improvements to be made to the approaches.

Inputs:

Links:

Risk & Issue Management Techniques Page

Outputs

Resource Management

Task:

Review effectiveness of resource management, productivity and optimise.

Review the programme resource management plan for the remainder of the tranche.

Review the resource management strategy that will be required for the remainder of the programme.

Guidance:

The achievement of a major outcome means that a significant transition has now happened, so it is the opportunity to review the effectiveness of transition resources as well as delivery resources. Resources to support sustaining the business to achieve benefits may still be needed, the resource plan should be checked for this.

This is a good moment to analyse the effectiveness of business transition resources, the change team and pick up lessons for future transitions and tranches.

Based on the review here, there may be a need to revise the resource management strategy and/or resource management plan for the programme, as well as the impacts on the projects delivering the capability.

Inputs:

Links:

Resource Management Techniques Page

Outputs

Finance and Business Case

Task:

Refine finance plans to accommodate any changes.

Review effectiveness of financial forecasting and address causes of weakness.

Review the funding strategy and anticipated costs.

Guidance:

The review should principally focus on the ongoing financial viability of the programme and, in particular, the availability of funds to support it. The balance of benefits and costs should have been under review all the way along, this is the opportunity to stand back and re-think against the bigger picture of organisational context.

The review should assess the accuracy of the estimates being provided for costs and benefits. These should be re-forecast and a revised Business Case produced to justify the programme continuing.

Funds to mobilise the programme and put the infrastructure in place need to be ring fenced to ensure availability.

Inputs:

Links:

Finance & Business Case Techniques Page

Outputs

Portfolio Office

Click to expand guidance.

Task:

Provide analysis and data to support the review.

Provide analysis data on governance performance.

Refresh the Comms Plan and ensure that it deals with the short term launch arrangements.

Click to expand guidance.

Task:

Provide analysis and data to support the review.

Provide analysis data on governance performance.

Refresh the Comms Plan and ensure that it deals with the short term launch arrangements.

Guidance:

You may need to be part of the review or have access to reviews to enable it to happen. In particular you should be monitoring for overlaps from other initiatives that affect the Blueprint, double counting of benefits or project overlaps.

New organisational standards and lessons from other programmes should be factored into the revisions.

Mobilisation may mean more pressure on your resources if the programme needs help.

Input:

Output:

Theme tasks for Portfolio Office: